What goes into the bid?
Keep a record of the construction detail you priced, the unit you measured, and the source of your cost. BidBench carries these choices through to the itemized export.
SMACNA duct construction
HVAC Duct Construction Standards — Metal and Flexible covers duct fabrication and installation. The third edition is identified as SMACNA 1966-2005. The fourth edition is ANSI/SMACNA 006-2020. Select the edition cited in the project documents under Estimate settings.
On a duct item, open Spec & pricing to record design pressure, material, sheet thickness, joint, reinforcement, seal class, support detail, and a drawing or table reference. The estimator selects the construction details from the contract documents and applicable standard. BidBench records those decisions for review.
Gordian’s RSMeans Mechanical Costs
The 2026 book is the 49th annual edition. It organizes mechanical unit costs by CSI MasterFormat and assemblies by UniFormat II. Its reference sections cover crew makeup, equipment, and location adjustments.
- Match the scope and unit. Look up a comparable task. A price per pound and a price per foot use different quantities. For straight duct, BidBench can calculate net sheet area from outside dimensions and run length. An estimator-entered sheet weight converts that area to pounds. Add seams, reinforcement, fittings, and waste separately where the scope calls for them.
- Separate direct costs from markup. BidBench totals material, equipment, and hours at the project labor rate. Use direct-cost inputs so overhead and profit are applied once.
- Record where the numbers came from. Save a supplier quote or company cost reference, its date, and an optional book edition and line reference. Use the book’s applicable geography and period when comparing it with local quotes.
The starter prices are examples. Commercial integration of Gordian’s cost data requires its written permission. The workspace supports your own prices and references.